UpdateI just got off the phone with the MSHA project manager and he said that Cline was in the office last wek to address those revision requests that I was speaking about last week. They addressed them but were sent back with some new revisions to the ventilation and roof plans. I asked Bill how long it will take for CMK to recieve the approvals and he stated that it could take another few weeks. I asked, if Cline submitted the revisions within the next couple of days would they recieve their approvals beofre December 31st and he said that it's still possible. So, yet again I think that we are still at a 50/50 for approvals. I will be calling back on Thursday for a new status update.