One of the mill expansion project completed to dateAnd completed with production revenue. From the Q2 report:
The work to install the induction furnaces and related hydraulic and electronic equipment
has now been completed and work on the vault to store dore production was also completed. There are some additional civil works pending completion and it is expected that in late February 2014 the Company will be able to commence testing of this new production process.
The capital projects are installation of refurbished 10` by 10` ball mill, construction of a new 60` by 12` thickener tank
and installation of furnaces and related infrastructure to produce dore bars as opposed to precipitate.
Read more at
https://www.stockhouse.com/companies/bullboard/v.rct/rochester-resources-ltd#cHPSBUYMzrlOOA1w.99
There are three capital projects
in progress which require completion in order to see significant increases in mill operations. The capital projects are installation of refurbished 10` by 10` ball mill, construction of a new 60` by 12` thickener tank and installation of furnaces and related infrastructure to produce dore bars as opposed to precipitate.