RE:West basin development timeline PLS ...
1 year to drill define 50-100 M lbs in the west end - 840 etc
2 years to get throught the EA process
1.5 year to strip and concurrent mill & infra structure build out
= 4.5 years to production
start ug development and concurrent water management structures
finances: sell 50Mlbs at $50/lb for delivery subsequent to production start.