Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Quote  |  Bullboard  |  News  |  Opinion  |  Profile  |  Peers  |  Filings  |  Financials  |  Options  |  Price History  |  Ratios  |  Ownership  |  Insiders  |  Valuation

Lydian International Ltd T.LYD


Primary Symbol: LYDIF

Lydian International Ltd is a gold focused mineral development corporation engaged in exploring and developing precious metals assets located in Armenia and Georgia. Its main project is Amulsar Gold Project (Amulsar) in Armenia. It owns the Amulsar Project, through its wholly-owned subsidiary Lydian Resources Armenia. Amulsar is a compelling opportunity for a large scale, low cost operation utilizing open pit mining and conventional heap leach processing.


OTCPK:LYDIF - Post by User

Post by portteron Feb 22, 2018 3:52pm
52 Views
Post# 27604623

News

News
Lydian Provides Construction Update for Its Amulsar Gold Project
TORONTO, Feb. 22, 2018 -- Lydian International Limited (TSX:LYD) (“Lydian” or the “Company”) today announced an update
for construction progress at its 100%-owned Amulsar Gold Project in Armenia (“Amulsar”). With scheduled average annual
production of 225,000 gold ounces over an initial 10-year mine life, Amulsar will be among the most significant new gold mines
to start operations this year.
Construction activities at Amulsar continue to progress well in key areas. Engineering is essentially complete, procurement is
approaching 90%, and construction work is more than 50% complete. Earthworks are largely complete in critical areas, with
the mine haul road and barren rock storage facility representing the largest remaining areas of work. Current construction
activities are largely focused on concrete and steel works in the crushing and screening area, the overland conveyor corridor,
and the ADR facilities.
First gold production remains on track for Q3 2018, although some areas have progressed slower than planned. This is due, in
large part, to unfavorable geotechnical conditions in several areas that required mitigation and pushed certain construction
activities into the winter season. Winter conditions typically continue through mid-April, but have been manageable to date.
Lost work days due to weather are within the scheduled allowance. Schedule risks are now reduced given that critical
earthworks are largely complete and contractor productivities are better known at this stage of the project.
Management is in the process of preparing a definitive capital cost estimate. This is a customary review at this stage of the
project with engineering largely complete, major equipment supply contracts in place, construction well advanced, and
operational readiness activities underway. While refinements are ongoing, management anticipates pre-production capital
costs will increase by approximately 10-12% above the current estimate of $383 million. The major components of this
increase are the costs directly and indirectly related to geotechnical mitigation efforts, scope changes, and schedule
extension.
Howard Stevenson, President and Chief Executive Officer of Lydian stated, “We are pleased with our overall progress to date,
aside from the geotechnical challenges experienced last fall. While the capital cost estimate has increased, we have
progressed to a point of having much greater certainty for our cost estimate to complete the project. As we enter into the final
stages of Amulsar’s development, we remain focused on delivering a significant and high-quality operation with our ongoing
dedication to health, safety, and the environment.”
Construction Highlights
Mine Operations
• Five Caterpillar 789 haul trucks, the Caterpillar 6040 hydraulic shovel, and the Caterpillar 994 front-end-loader have been
commissioned;
• Four additional haul trucks expected to be commissioned during 1Q 2018;
• Simulators in use to screen and train equipment operators;
• Initial mine haul road cut complete from open-pits to the primary crusher area; and
• Expansion of mine haul road to full design width starting Q1 2018.
Materials Handling System
• Mitigation of geotechnical conditions resulted in more concrete work being performed in winter conditions than planned.
Contractors are performing well;
• Screening building concrete is complete, crushing area foundations are on pace for Q1 2018 completion;
• Installation of pre-fabricated buildings and structural steel for screening area are advancing concurrently;
• The pre-cast concrete tunnel has been installed in the coarse ore stockpile area together with the reclaim feeders and
associated structural steel;
• Earthworks along the conveyor system being handed over for progression to concrete and steel works; and
• Overland conveyor galleries have been installed along a distance of 1.4 kilometers.
Heap Leach Facility
• Bulk earthworks are largely complete with slope contouring continuing ahead of geomembrane liner placement starting
in the spring 2018; and
• Process and storm ponds ready for liner installation.
Processing Facilities
• The majority of the ADR structural steel and equipment is on site, the balance is on schedule for Q1 2018 delivery;
• Earthworks and foundations are complete;
• Structural steel for carbon-in-column tanks has been set; and
• Area E-house is on site and ready for placement on foundation.
Infrastructure
• 35 kV electrical distribution towers are in place and power line stringing is in progress;
• Substation concrete progressing ahead of main substation installation;
• The E-house is en route Q1 2018; and
• Water management and storage system design is complete.
Sustainability
• Amulsar was pre-operationally certified as being in compliance with the International Cyanide Management Code; and
• A draft of the Jermuk National Park Establishment Government Decree has been prepared and is under review.
To view construction photos and videos, please visit www.lydianinternational.co.uk.
About Lydian International Limited
Lydian is a gold developer focusing on construction at its 100%-owned Amulsar Gold Project, located in south-central
Armenia. Amulsar will be a large-scale, low-cost operation with production expected to begin in the third-quarter of 2018. Gold
production is targeted to average approximately 225,000 ounces annually over an initial 10-year mine life, making Lydian one
of the largest gold producers to emerge during 2018. Open pit mining and conventional heap leach processing contribute to
excellent scale and economic potential. Estimated mineral resources contain 3.5 million measured and indicated gold ounces
and 1.3 million inferred gold ounces as outlined in the Q1 2017 Technical Report. Existing mineral resources beyond current
reserves and open extensions provide opportunities to improve average annual production and extend the mine life. Lydian is
committed to good international industry practices in all aspects of its operations including production, sustainability, and
corporate social responsibility. For more information and to directly contact us, please visit www.lydianinternational.co.uk.
For further information, please contact:
Doug Tobler, CFO
+1 720-307-5087 (d) or +1 303-905-4442 (m)
Pamela Solly, Vice President of Investor Relations
+1 720-464-5649 (d) or +1 303-810-4863 (m)
Or: moreinfo@Lydianinternational.co.uk
<< Previous
Bullboard Posts
Next >>