Estimated SART Capex is $11 to $22 million USD, and operating cost is $0.45 USD per cubic meter treated. At 600 cubic meters per hour, the daily cost would be $6480 USD or the cost of 1 metric ton of copper at $3 USD/lb. Daily copper production would be around 10 metric tons. So there should be a healthy margin associated with a SART plant.
Keep in mind that this plant would be a new like adding a new mine on to the existing Don Mario mine.