RE:RE:TT1 torch As per the press release for the intitial torch offering for Client A (Iron Ore Pellitizer Behemoth):
"It is expected, with multiple orders, that PyroGenesis would source long lead items ahead of time, and as such, it is expected that the time from contract to final assembly/installation at a client’s facility will be from a couple of weeks up to four (4) months."
Given the initial torch offer for iron ore pellitization is not "multiple orders" quite yet and just a single torch, I imagine we are looking at something more in the 2-4 week range for the initial torch. So hopefully Client A has that installed soon if it doesn't already and we can get a move on future orders! Excellent times ahead; plasma torches are becoming proven technology.
When we have future torch orders for multiple iron ore pellitizer torches, I expect longer lead times given this statement so keep that in mind when Client A begins adoption of these torches... exciting.
I am just guessing here but my assumption is that the iron ore pelltizer torches are more standardized given the process they are used for vs. a plasma torch for tunnelling which likely has varying requirements depending on the user needs.
StairwayTo wrote:
Great news today.
This again validates PYR technology.
Question for the more knowledgable people on PYR torches,
How is a tunneling torch compares with the iron ore torches?
My undesrtanding was that PYR torches are some what similar one an other, just differ in the application.
So now we have a timeline of designing, manufacturing and delivering (in USA) to 6 months +.
We also have a price tag, which is great information.
Would 6 months applies to each torch for eventual iron torch customer?