RE:RE:RE:RE:RE:RE:RE:RE:RE:Technically don't get itFrom the MetalsNews article:
From there, we will look to move into the construction phase, where we build our solar facility, along with our finishing and refinery facility. We were looking to go into production in the fourth quarter of this year. We've had some delays getting permits, so it might set the whole program back a month or two and it may not get into production until first or second quarter of 2022. But right now, the plan is still to be in production by the end of the fourth quarter of 2021. Buyhigheatchips wrote: From the Mar 25th NR:
Additionally, the Company has taken proactive steps in ordering specific components of the processing units, which have the longest lead time for delivery to ensure the on-time startup of our processing facilities in the fourth quarter of 2021.