RE:Not impressed by construction start date.Hey Goatburner, have you driven by the OLD REFINERY lately?
There is a level of BS from FCC management here and I not sure what its about. I can tell you a pre-engineered steel structure if you ordered it today it is 10 to 12 months out. If you went conventional steel you might see it in May June. My guess is we would have a combination of the two. I would guess at a timeframe of 12 months and that could be shortened by how much pre-work is done now. And that my friends is an aggressive shedule and we have not even talked about process equipment. Will we see production in 2022? I doubt it now.
Oh and the permits, I cry BS on that. I know getting permits is a process and then some. The tri-town municipality would be easier that the GTA and enough time has passed so what is going on?
BLACK MASS. Remember that?! I would hope we start to see some revenue from that process in a month or two. If not then we are in a real WTF scenario.
So Trent its time to talk to the shareholders. What about it?