RE:RE:RE:RE:Cgx NewsFrom the very beginning - Kawa was designed to be plugged and abandoned. Kawa was never intended to be preserved nor would be used for a DST (flow test).
I cannot recall a single instance where a frontier exploration deepwater well was flow tested immediately after discovery. I don't know where that came from on this board - but, it's completely inaccurate.
DSTs are usually performed on appraisal wells. The reason is that the well design on appraisals are sufficient to support hydrocarbon flow.
As part of DST, you also need to order specialized equipment from service companies in advance and configure the rig to perform a DST.
Again, during CGX / Frontera October 2020 presentation this was all communicated to investors:
1. Kawa would be P&Ad
2. No DST (or flow test)