RE:How long does it take to make 4 plasma Torches? I actually thought this was a fair question as Peter did say they could make them faster. Midtownguy's response also made sense. The customer may have needed time to get the electrical infrastructure in place.
chickendinner wrote:
The news release dated sept 14 2021 Pyrogenesis says that it has received an order to supply four (4) high powered plasma torches together with ancillary equipment to a client (“Client B”), for approximately $6MM. and as of this morning Steve Mccormick goes on to say on Proactive youtube channel that order will be completed either end of year or 1st quarter of 2023. so by my calculations Pyro is building 1 torch per quarter thats 4 a year. why is it taking so long to build? not going to crack open the champagne bottle when they get the 130 torch order because it will take 32 years to complete. wow
Am I wrong here?