RE:The torch landed on July 5th The 90 days to "get an extension cord" will be 90 from July 31 as July 5th press
"
The SAT was initially scheduled to be completed for the end of July 2022. The Client has recently informed PyroGenesis that they would prefer to extend the process by up to an additional 90 days. Lets not forget that at the June 21 agm the CEO clearly stated the install was on sched as per press releases and then 2 weeks later stated that vale needed the 90 days. Apparently no one from pyro noticed that no one had "installed the wall plug"
Quite amazing that no one noticed in the years of prep and planning and then incredibly long , almost 5 months, of packing and shipping.
I have to wonder did they give the project manager severance pay or fire him on the spot without pay because obviously Peter wouldn't have mislead shareholders in the agm so someone must have mislead him about the infrastructure status or been severely incompetent .
blackriver1 wrote: I wonder if the 90 day extension was from when the torch landed or from the end of July ?
Either way it is getting closer and closer to torch time, if it is from July 5th the date is just around the corner, if end of the month, it still should be in 2022. LFG
Big things coming ???