RE:RE:RE:RE:Nickel pricePage 16 of CNC's PEA provides for 8,059 operating hours per year, which is 22.08 hours per day, 365 days a year.
Still hold the same convictions?
idlefreebird wrote: some of there numbers things don't add up...
120,000 tpd milling for 365 days for 43.8 million tpa would mean they run 365 days...there isn't a mill on this universe that don't have at least a monthly shutdown and this size of operation could be a two day a month as lifters and liner changes is a big job for this size of mill...