Here is an old article on moving 6.2 klm of hyw 101and keeping in mind an additional 20 klm of road was built to get ore to mill also portion of lake was dammed and fish relocated to the other side ...glta P.S. Timmins is mining....
"We found more ore (at the Dome site), so we'll be able to do more pre-stripping on the Pamour," he says. "We won't have to start supplying ore (from the Pamour site) until August or September."
In order to accommodate the excavation, they are building a new 6.2 km portion of Highway 101 East to extend around the site, and plans are in process to move the top portion of Three Nations Lake next summer.
Read related story>> https://www.northernontariobusiness.com/regional-news/timmins/joint-venture-has-big-plans-for-pair-of-properties-0705-363659