PolyMet Reports Results for Year Ended December 31, 2018
PolyMet Mining Corp. (“PolyMet” or the “company”) TSX: POM; NYSE American: PLM – today reported that it has filed its financial
results for the year ended December 31, 2018. PolyMet is fully permitted to construct and operate the NorthMet
copper-nickel-precious metals mine and processing plant located near Hoyt Lakes, Minnesota.
The financial statements have been filed at
www.polymetmining.com and on SEDAR and EDGAR and have been prepared in accordance with International Financial Reporting
Standards. All amounts are in U.S. dollars. Copies can be obtained free of charge by contacting the Corporate Secretary at First
Canadian Place, 100 King Street West, Suite 5700, Toronto, Ontario M5X 1C7 or by e-mail at info@polymetmining.com.
Highlights and recent events for 2018 and 2019 to-date
- In March 2019, the company received the federal Record of Decision and wetlands permit from the U.S.
Army Corps of Engineers, which is the last key permit or approval needed to construct and operate the NorthMet Project.
- In March 2019, the company and Glencore AG (“Glencore”) agreed to extend the term of the outstanding
debentures to provide the company time to prepare for and complete a rights offering by June 30, 2019, fully backstopped by
Glencore, to raise sufficient funds to repay all outstanding debt.
- In December 2018, the company received all Minnesota Pollution Control Agency permits for NorthMet
for which the company had applied, including air and water permits.
- In November 2018, the company received all Minnesota Department of Natural Resources permits for
NorthMet for which the Company had applied, including the Permit to Mine, dam safety and water appropriations permits.
- In June 2018, the company and U.S. Forest Service completed the federal land exchange giving PolyMet
title and control over both surface and mineral rights in and around the NorthMet ore body.
- In March 2018, the company issued an Updated Technical Report under NI 43-101 incorporating process
improvements, project improvements and environmental controls described in the Final Environmental Impact Statement and draft
permits. The update also included detailed capital costs, operating costs, and economic valuations for the mine plan being
permitted, as well as a discussion of potential future opportunities.
Goals and objectives for the next twelve months
PolyMet’s objectives include:
- Maintain political, social and regulatory support for the project;
- Complete project optimization plan;
- Complete project implementation plan;
- Strengthen balance sheet through restructuring or repaying outstanding debt; and
- Execute construction finance, subject to typical conditions precedent.
|
Key Balance Sheet Statistics
(in ‘000 US dollars, except per share amounts)
|
|
|
December 31, 2018
|
|
December 31, 2017
|
Balance Sheet |
|
|
|
|
|
|
|
Cash & equivalents |
|
$ |
13,857 |
|
|
$ |
6,931 |
|
Working capital (see note) |
|
|
(225,359 |
) |
|
|
(138,057 |
) |
Total assets |
|
|
485,629 |
|
|
|
409,042 |
|
Total liabilities |
|
|
300,587 |
|
|
|
210,367 |
|
Shareholders’ equity |
|
$ |
185,042 |
|
|
$ |
198,675 |
|
Note: Maturity dates for the convertible and non-convertible debentures
were extended to provide time to complete a rights offering to raise sufficient funds to repay all outstanding debt. Glencore
has agreed to fully backstop the rights offering. |
|
Key Income and Cash Flow Statement Statistics
(in ‘000 US dollars, except per share amounts)
|
|
Twelve months ended
December 31, 2018
|
|
Eleven months ended
December 31, 2017
|
Income and Cash Flow Statement |
|
|
|
|
|
|
General & administrative expense |
|
$ |
7,070 |
|
$ |
6,125 |
Other Expenses: |
|
|
|
|
Finance & Other |
|
|
544 |
|
|
404 |
Non-cash rehabilitation accretion |
|
|
1,796 |
|
|
1,776 |
Non-cash loss on fair value update |
|
|
971 |
|
|
- |
Non-cash loss on debenture modification |
|
|
4,109 |
|
|
- |
Non-cash loss on disposals |
|
|
553 |
|
|
1,793 |
|
|
|
|
|
Loss for the period: |
|
|
15,043 |
|
|
10,098 |
Other Comprehensive (Income) |
|
|
- |
|
|
202 |
|
|
|
|
|
Loss per share |
|
|
0.05 |
|
|
0.03 |
Investing Activities |
|
|
|
|
NorthMet Project |
|
$ |
57,353 |
|
$ |
21,669 |
|
|
|
|
|
Weighted average shares outstanding |
|
|
320,495,981
|
|
|
318,891,961
|
|
|
|
|
|
- Loss for the twelve months ended December 31, 2018, was $15.0 million compared with $10.1 million for
the prior year period. Excluding non-cash compensation, general and administrative expenses for the twelve months ended December
31, 2018, were $5.3 million compared with $4.8 million for the prior year period.
- PolyMet invested $57.3 million cash into its NorthMet Project during the twelve months ended December
31, 2018, compared with $21.7 million in the prior year period. The current year includes $21.1 million in wetland credit
purchases and $10.0 million to fund the environmental rehabilitation trust required under the Permit to Mine.
About PolyMet
PolyMet Mining Corp. (www.polymetmining.com)
is a publicly traded mine development company that owns 100 percent of Poly Met Mining, Inc., a Minnesota corporation that controls
100 percent of the NorthMet copper-nickel-precious metals ore body through a long-term lease, and owns 100 percent of the former
LTV Steel Mining Company processing facility, located approximately seven rail miles from the ore body in the established mining
district of the Mesabi Iron Range in northeastern Minnesota. Poly Met Mining, Inc. has completed its Definitive Feasibility Study
and received all permits necessary to construct and operate the NorthMet Project. NorthMet is expected to require approximately two
million hours of construction labor, create approximately 360 long-term jobs directly, and generate a level of activity that will
have a significant multiplier effect in the local economy.
PolyMet Disclosures
This news release contains certain forward-looking statements concerning anticipated developments in PolyMet’s operations in the
future. Forward-looking statements are frequently, but not always, identified by words such as “expects,” “anticipates,”
“believes,” “intends,” “estimates,” “potential,” “possible,” “projects,” “plans,” and similar expressions, or statements that
events, conditions or results “will,” “may,” “could,” or “should” occur or be achieved or their negatives or other comparable
words. These forward-looking statements may include statements regarding the ability to receive environmental and operating
permits, job creation, and the effect on the local economy, or other statements that are not a statement of fact. Forward-looking
statements address future events and conditions and therefore involve inherent known and unknown risks and uncertainties. Actual
results may differ materially from those in the forward-looking statements due to risks facing PolyMet or due to actual facts
differing from the assumptions underlying its predictions.
PolyMet’s forward-looking statements are based on the beliefs, expectations and opinions of management on the date the
statements are made, and PolyMet does not assume any obligation to update forward-looking statements if circumstances or
management’s beliefs, expectations and opinions should change.
Specific reference is made to risk factors and other considerations underlying forward-looking statements discussed in
PolyMet’s most recent Annual Report on Form 40-F for the fiscal year ended December 31, 2018, and in our other filings with
Canadian securities authorities and the U.S. Securities and Exchange Commission.
The Annual Report on Form 40-F also contains the company’s mineral resource and other data as required under National
Instrument 43-101.
The TSX has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.
Click here to subscribe to Mobile Alerts for PolyMet Mining Corp.
Media
Bruce Richardson, Corporate Communications
Tel: +1 (651) 389-4111
brichardson@polymetmining.com
Investor Relations
Tony Gikas, Investor Relations
Tel: +1 (651) 389-4110
investorrelations@polymetmining.com
View source version on businesswire.com: https://www.businesswire.com/news/home/20190329005167/en/