- 10,470 OUNCES OF GOLD PRODUCED
- 4,069 OUNCES OF GOLD PRODUCED IN DECEMBER
- COMMERCIAL PRODUCTION ACHIEVED IN DECEMBER
VANCOUVER, Jan. 9, 2018 /CNW/ - Rye Patch Gold Corp. (TSX.V:
RPM; OTCQX: RPMGF; FWB: 5TN) (the "Company" or "Rye Patch") reports Q4 2017 production metrics at the Company's flagship
Florida Canyon mine in Pershing County, Nevada.
Production highlights for Q4 2017 as compared to Q3 2017 and the Company's preliminary economic assessment "Plan" (see
description below) are:
- Produced 10,470 ounces of gold and 5,447 ounces of silver in Q4;
- Mined 2,372,000 tons of ore (30 percent above Plan);
- Crushed 2,291,000 tons of ore (27 percent above Plan);
- Placed 25,434 ounces of gold on the pad;
- Maintained a consistent gold grade of 0.011 opt including over liner material; and
- Realized a stripping ratio of 0.55 which is significantly lower than Plan.
Gold production continued its upward trend, increasing 31 percent in Q4 compared to Q3. In December, gold production was
4,069 ounces of gold and 1,996 ounces of silver. Total precious metal production for the fourth quarter was 10,470 ounces
of gold and 5,447 ounces of silver.
Gold sales benefitted from a combination of selling into the forward sales contract and spot price with a realized gold price
of $1,278. Silver was sold at spot price during the quarter and realized an average price of
$16.65. A total of 9,532 ounces of gold and 6,756 ounces of silver were sold during the
quarter.
Mining and crushing rates are now consistently outperforming the original Plan by 30 percent and 27 percent
respectively. As a consequence, the crusher throughput has been increased to 750,000 tons per month of ore crushed and
stacked to the South Heap Leap Pad on a go-forward-basis, representing a 25 percent increase over the original Plan. The
crusher continues to demonstrate operational performance above 750,000 tons per month, and a study to determine the optimal
throughput and associated capital requirements will be completed in 2018.
The waste to ore stripping ratio of 0.55 continues to be much lower than 1.47 projected in the original Plan. The mine is
realizing better continuity of grade and tonnage than forecast in the block model. An average of 17 percent increase in ore
tons, a 7 percent increase in gold grade, and a 25 percent increase in gold ounces as compared to the resource block model has
been achieved. As a result of internal revisions to Florida Canyon's mining plan and changes to the production sequencing,
the Company will be using an average stripping ratio 0.8 as a guide for 2018 and an overall stripping ratio of 1.05 for the
life-of-mine schedule.
Gold ounces placed on the pad averaged 8,478 ounces of gold placed per month in Q4. Projected recoveries of 71 percent
remain consistent with gold recoveries achieved to date. Based on gold ounces stacked and gold ounces poured, the South
Heap Leach Pad (SHLP) is performing with 70 percent of the recoverable gold ounces being produced from the primary leach cycle.
The remaining 30 percent will be produced during secondary and tertiary leach cycles. To date, only primary leaching
has occurred to maximize cash flow and determine the optimal leach cycle. Primary, secondary and tertiary leach cycles will begin
in 2018 as the second lifts of ore are placed on top of the first lift.
Based on the Company's six months of operating experience, differences have become apparent between current gold production
and that forecast under the Plan. These differences relate to the six-month construction/weather delay, the operational
challenges associated with the mining fleet in Q1 and Q2, and a recognition that the process of putting tons under leach to the
production of gold dore' takes 60 days. This impacts solely the timing of gold production, not the amount of gold which is
ultimately produced.
Florida Canyon Mine - South Heap Leach Pad ramp up data
|
|
|
|
|
|
|
Three months
ended
December 31,
2017
|
Three months
ended
September 30,
2017
|
Three months
ended
June 30,
2017
|
Three months
ended
March 31,
2017
|
12 months
ended
December 31,
2017
|
Ore mined
|
tons
|
2,371,625
|
2,443,745
|
1,560,342
|
612,578
|
6,988,290
|
Waste mined
|
tons
|
1,295,314
|
1,331,761
|
1,953,817
|
1,713,217
|
6,294,109
|
Total mined
|
tons
|
3,666,939
|
3,775,506
|
3,514,159
|
2,325,795
|
13,282,399
|
Stripping ratio
|
|
0.55
|
0.54
|
1.25
|
2.80
|
0.90
|
|
|
|
|
|
|
|
Ore and overliner crushed
|
tons
|
2,291,063
|
1,994,765
|
1,542,031
|
746,241
|
6,574,100
|
Ore and overliner stacked on pad
|
tons
|
2,312,268
|
1,985,860
|
1,540,544
|
571,884
|
6,410,556
|
Ounces sent to HLP
|
|
25,434
|
21,376
|
14,792
|
4,621
|
66,223
|
|
|
|
|
|
|
|
Grade ore
|
ounce
|
0.011
|
0.011
|
0.010
|
-
|
0.011
|
Grade overliner
|
ounce
|
0.011
|
0.011
|
-
|
0.008
|
0.011
|
Combined grade
|
|
0.011
|
0.011
|
0.010
|
0.008
|
0.011
|
|
|
|
|
|
|
|
Gold absorbed onto carbon
|
Ounces
|
10,509
|
8,125
|
7,480
|
2,091
|
28,205
|
Gold produced Dore
|
Ounces
|
10,471
|
7,982
|
7,075
|
2,455
|
27,983
|
Silver produced Dore
|
Ounces
|
5,447
|
5,239
|
5,603
|
4,529
|
20,818
|
All four newly purchased CAT 785C haulage trucks are in operation. In addition, the planned Carbon-in-Column (CIC) plant expansion is complete. The newly installed second CIC plant will nearly
double the processing capacity with throughput increasing from 18,000 solution tons per day to 30,000 solution tons per
day. The additional flow will allow for more square footage to come under leach and increase gold production. The
additional CIC capacity will be operational in early Q1 of 2018.
Based on the above planned operational performance of the mine and the crusher and the actual versus model recovery and
predictability of the South Heap Leach Pad, the Company has determined that the Florida Canyon mine achieved commercial
production in December 2017.
"Plan" refers to the Company's preliminary economic assessment effective March 16, 2016, and dated January 27, 2017,
titled "Amended Technical Report – Preliminary Economic Assessment for the Florida Canyon Mine, Pershing County, Nevada" available on the Company's website and under the Company's profile at www.sedar.com.
Mr. William Howald, AIPG Certified Professional Geologist #11041, Rye Patch Gold's CEO and
President with a BSc. in Geological Engineering, is a Qualified Person as defined under National Instrument 43-101. He has
reviewed and approved the contents of this news release.
About Rye Patch Gold Corp.
Rye Patch Gold Corp. is a Nevada based, Tier 1, mining company engaged in the mining
and development of quality resource-based gold and silver mines and projects along the established Oreana trend in west central
Nevada. Leveraging its strong financial position and cash to acquire the operating Florida
Canyon Gold Mine, Rye Patch Gold Corp. now controls a trend‑scale platform with mining operations, resource projects and
exploration upside.
The combination of operations and organic growth along a major Nevada gold trend positions
Rye Patch as an emerging mid-tier gold producer with tremendous value‑added potential. For more information, please visit our
website at www.ryepatchgold.com.
On behalf of the Board of Directors
'William Howald'
William C. (Bill) Howald, CEO & President
Forward-Looking Statements
This news release contains forward-looking statements relating to future plans and objectives of the Company, future
deliveries of gold, proposed operations of the Company including mine development, funding requirements, timeline for commercial
production, future events and conditions and other statements that are not historical facts, all of which are based on
assumptions and subject to various risks and uncertainties. The Company's actual results, programs and financial position could
differ materially from those anticipated in such forward‑looking statements as a result of the following assumptions and risk
factors, some of which may be beyond the Company's control. These assumptions and risk factors include: future deliveries of gold
pursuant to the forward gold price contract facility, the achievement of mine redevelopment plans and achievement of commercial
production; the availability of funds; the financial position of Rye Patch; the timing and content of work programs; the results
of exploration activities and development of mineral properties; the interpretation of drilling results and other geological
data; the reliability of calculation of mineral resources; the reliability of calculation of precious metal recoveries; the
receipt and security of mineral property titles; project cost overruns or unanticipated costs and expenses; fluctuations in metal
prices; currency fluctuations; and general market and industry conditions.
Forward-looking statements are based on the expectations and opinions of the Company's management on the date the
statements are made. The assumptions used in the preparation of such statements, although considered reasonable at the time of
preparation, may prove to be imprecise and, as such, undue reliance should not be placed on forward-looking statements. As
a result, the Company cannot guarantee that the Florida Canyon mine redevelopment and achievement of commercial production will
be completed on the terms and within the time disclosed herein or at all.
Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture
Exchange) accepts responsibility for the adequacy or accuracy of this release.
SOURCE Rye Patch Gold
View original content with multimedia: http://www.newswire.ca/en/releases/archive/January2018/09/c2197.html