BUENOS AIRES, Argentina, March 02, 2018 (GLOBE NEWSWIRE) -- AbraPlata Resource
Corp. (TSX.V:ABRA) (OTC:ABBRF) (Frankfurt:1AH) ("AbraPlata" or the "Company") is pleased to announce the
completion of an independent Preliminary Economic Assessment ("PEA") on the Company's 100% owned Diablillos silver-gold project,
located in Salta Province, Argentina. The results of the PEA demonstrate the potential technical and economic viability of
establishing an open pit silver-gold mine with mill complex on the Diablillos property. Highlights of the PEA are provided in Table
1 and the forecast annual silver-equivalent (“AgEq”) production and head grades are shown in Figure 1.
|
Table 1 - Summary of Diablillos Project PEA (all dollar amounts
in US$) |
Pre-Tax Net Present Value (“NPV”)7.5% |
$342
Million |
Pre-Tax Internal Rate of Return (“IRR”) and Payback |
40.7% and 2.9
years |
After-Tax
NPV7.5% |
$197 Million |
After-Tax IRR
and Payback |
30.2% and 3.1
years |
Average Head
Grade |
125.1 g/t Ag and
0.72 g/t Au |
Average Annual
Production |
9.8 Moz AgEq or
136,000 oz AuEq |
Mine Life |
8 years |
Average All-in
Sustaining Cost per Ounce Produced |
$7.52/AgEq oz or
$542/AuEq oz |
Initial
Capital |
$293 Million |
Metal Price
Assumptions |
Ag: $20.00/oz and
Au: $1,300/oz |
Calculated
Metal Net Smelter Return (“NSR”) Values |
Ag: $15.20/oz and
Au: $1,097/oz |
|
|
The PEA is preliminary in nature and includes inferred mineral resources that are too speculative
geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. There is
no certainty that PEA results will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic
viability.
Commenting on the results, Hernan Zaballa, Chairman of AbraPlata, stated, “We are very pleased with the robust
results of the Diablillos PEA. The PEA demonstrates that Diablillos has the potential to produce almost 10 million AgEq
ounces per year at a low all-in sustaining cost per ounce. While the main Oculto deposit does require pre-stripping, the average
grades are relatively high for an open pit mine. On the basis of historical drill results, our geological team believes that
there is strong potential to expand the high grade gold zones in the eastern portion of the Oculto deposit, which are not included
in the PEA pit shell. The gold-rich mineralization at Oculto and additional near-surface mineralization at satellite deposits
sets up the potential to extend the mine life and potentially strengthen the economics even more in future economic studies.”
The PEA was prepared under the guidance of lead consultant RPA Inc. of Toronto ("RPA") with input from GR Engineering Services
Ltd of Perth, Western Australia (“GRES”), and Saxum Engineered Solutions of Argentina (“Saxum”).
A cash flow valuation model for the Diablillos project was developed as part of the PEA. From metal prices
of US$20.00 per ounce silver and US$1,300 per ounce gold, Table 2 shows the sensitivity of estimated NPV of the project's cash
flows at various silver prices. Figure 2 shows the undiscounted annual and cumulative after-tax cash flows.
|
Table 2 - PEA Sensitivity to Silver Price |
Silver Price (US$/oz Ag) |
After-Tax NPV7.5% (US$) |
After-Tax IRR |
After-Tax Pay Back |
$16/oz
Ag |
$108 Million |
20.3 |
% |
3.7 Years |
$18/oz
Ag |
$153 Million |
25.3 |
% |
3.4 Years |
$20/oz Ag |
$197
Million |
30.2 |
% |
3.1
Years |
$22/oz
Ag |
$241 Million |
34.9 |
% |
3.0 Years |
$24/oz
Ag |
$285 Million |
39.5 |
% |
2.8 Years |
|
|
|
|
|
Project Description and Mineral Resource Estimate
The Diablillos property is located in the Puna of Argentina, in the Province of Salta, approximately 150 km
southwest of the city of Salta. The property comprises nine mineral leases acquired by AbraPlata in 2016 from SSR Mining Inc.
(formerly Silver Standard Resources Inc.), with several known occurrences of epithermal gold-silver mineralization.
Exploration work, conducted by a number of operators over the history of the project, includes 87,711 m of diamond and reverse
circulation drilling in 476 holes. This drilling has delineated the Oculto and Fantasma deposits, which are weathered
high-sulphidation epithermal gold-silver deposits hosted primarily in Tertiary volcanic and sedimentary rocks. The current
Mineral Resource estimates for the Oculto and Fantasma deposits are shown in Table 3.
|
Table 3 - Diablillos Mineral Resource Estimates – Effective
August 31, 2017 |
Deposit |
Category |
Tonnage |
Ag |
Au |
Contained Ag |
Contained Au |
(000
t) |
(g/t) |
(g/t) |
(000 oz
Ag) |
(000 oz
Au) |
Oculto |
Indicated |
26,850 |
93.0 |
0.85 |
80,300 |
732 |
Fantasma |
Indicated |
200 |
98.3 |
- |
650 |
- |
|
Total
Indicated |
27,100 |
93.1 |
0.84 |
80,940 |
732 |
Oculto |
Inferred |
1,000 |
46.8 |
0.89 |
1,510 |
29 |
Fantasma |
Inferred |
80 |
75.3 |
- |
190 |
- |
|
Total Inferred |
1,100 |
48.8 |
0.83 |
1,690 |
29 |
Notes:
- CIM definitions were followed for Mineral Resources.
- Mineral Resources are estimated at a cut off grade of 40 g/t AgEq for Oculto and 40 g/t Ag for Fantasma.
- Mineral Resources are estimated using long-term metal prices of US$1,500/oz Au and US$23/oz Ag.
- Average bulk density is 2.22 t/m3 for the Indicated category and 2.29 t/m3 for Inferred for Oculto and
2.00 t/m3 for both Indicated and Inferred categories for Fantasma.
- The estimate is constrained by pit shells for both Oculto and Fantasma.
- Numbers may not add due to rounding.
Production Summary
The PEA envisions conventional open pit mining methods utilizing contractor-operated truck and shovel operations. Oculto will
require approximately 18 months of pre-stripping of unmineralized overburden. The Oculto pit will have a mine life of eight
years (excluding pre-stripping) and be supplemented by a small amount of material from the nearby Fantasma deposit. The life
of mine (“LOM”) strip ratio will be 3.2:1, or 4.6:1 including pre-stripping. The final pit shells and waste dump are shown in
Figure 3.
Process Plant
The processing facility has been selected as a conventional silver processing plant that incorporates crushing,
grinding, agitated leaching, counter current decantation (“CCD”), cyanide recovery, Merrill-Crowe zinc precipitation, refining and
tailings disposal. The design basis for the process plant is 6,000 tonnes of mineralized material per calendar day (“tpd”), or 2.19
million tonnes of mineralized material per annum. The equipment has been sized to achieve this throughput with an operating
availability of 70% in the crushing circuit and 91.3% in the grinding and cyanidation sections.
The three-stage crushing circuit delivers crushed material to a fine ore storage bin. The crushed material
is withdrawn from the bin to feed a 6.0 MW ball mill that has a centrifugal gravity recovery circuit included in the design.
Ground material is fed into six leach tanks where the silver and gold will be dissolved. The leached slurry is then sent to
the CCD circuit where the silver and gold solution is washed away from the solids before being sent to the Merrill-Crowe zinc
precipitation circuit to recover the silver and gold. The precious metals are then refined and poured into Dore bars in the
refinery. The washed solids from the CCD circuit are sent to the cyanide recovery circuit to maximize the amount of cyanide
that can be recirculated and the resulting slurry is sent to cyanide detoxification before being pumped to the final tailings
storage facility (“TSF”).
A number of trade-off studies looked at the treatment options for the project’s high and low grade mineralized
material. A range of throughput options were investigated for high grade milling at 4,000 tpd, 6,000 tpd and 8,000 tpd.
The optimum throughput for high grade mineralized material was determined to be 6,000 tpd.
For the lower grade mineralized material, two different treatment options were considered, being either heap
leaching (“HL”) or operating the process plant at a higher throughput (“HTP”) than the nominated 6,000 tpd. This was achieved
by allowing the grind size of the material exiting the grinding section to increase from a P80 of 75 micron to a
P80 of 100 micron, increasing the nominal throughput rate to 7,500 tpd.
Recoveries
The recovery of silver and gold was calculated as a function of the head grade of the mineralized material treated. For both
the standard milling circuit and the HTP option, the same regression equations were used, with an additional lowering of the
recovery with the coarser particle size in the HTP option. The gold recovery for HTP was lowered by an additional 4% from the
regression calculation, whilst the silver recovery was lowered by 8%. Life of mine average silver and gold recovery for the
standard milling option are 82% and 86%, respectively, and the HTP milling option achieves 55% and 81%, respectively.
Project Capital Costs
The capital costs ("CAPEX") for the contemplated open pit mine, process plant and supporting infrastructure for the Diablillos
project are estimated at US$311 million. Initial capital costs are estimated at US$293 million, including US$91 million in
pre-stripping costs at the Fantasma and Oculto deposits and contingencies of US$32 million. The capital costs for the process
plant were based on input from GRES, which specializes in fixed price engineering design and construction services to the resources
and mineral processing industry. Other capital costs were estimated from a variety of sources including comparative analysis
of other operations, derivation from first principles, equipment quotes and factoring from other costs contained within the
PEA. The project CAPEX is summarized in Table 4.
|
|
Table 4 - Summary of Capital Cost Estimates |
|
Description |
Cost US$000s |
Surface Mining |
93,308 |
Processing |
69,192 |
Site Infrastructure |
35,195 |
Owner Costs |
17,336 |
Indirect Costs |
45,645 |
Contingency & Other Provisions |
32,282 |
Initial Capital Cost |
292,959 |
Sustaining Capital |
4,998 |
Closure |
13,000 |
Total
Capital Costs |
310,957 |
|
|
Operating Costs
The operating cost estimate ("OPEX") is based on a contractor-operated truck and shovel mining operation, conventional processing
facility, and TSF. Mine operating cost estimates are provided in Table 5 and unit OPEX per ounce produced is shown in Table
6. The PEA estimates that the OPEX will average US$6.52 per ounce of AgEq (or US$470 per ounce of AuEq).
|
|
|
Table 5 – Mine Operating Cost Estimates |
|
|
Operating Costs |
US$ per tonne mined |
US$ per tonne milled |
Mining – waste |
3.00 |
8.75* |
Mining - mineralized material |
3.60 |
3.23 |
Standard Milling |
|
14.63 |
Standard Milling G&A |
|
2.92 |
HTP Milling |
|
12.68 |
HTP Milling G&A |
|
2.33 |
* Note: excludes capitalized stripping costs.
|
Table 6 - Operating Costs per Ounce Produced |
Operating Costs |
US$ per AgEq oz Produced |
US$ per AuEq oz Produced |
Surface Mining |
2.57 |
186 |
Salta Province Royalty |
0.34 |
24 |
Processing |
3.02 |
218 |
G & A |
0.59 |
43 |
Total Operating Cost |
6.52 |
470 |
|
|
|
Opportunities to Enhance Value
The PEA pit shell focuses on the most profitable portion of the Mineral Resources, accounting for approximately 60% of the tonnage
contained within the Mineral Resource pit shell. The PEA does not contemplate mining the eastern portion of the Oculto
deposit due to the depth of mineralization, which would result in an increased stripping ratio. Historical drilling in the
eastern portion of the Oculto deposit has encountered high grade gold mineralization in metamorphic basement rocks (e.g.
DDH-87-007A intersected 16.7 g/t Au and 39.2 g/t Ag over 10.6 metres starting at 210 metres down hole). A recent
comprehensive review of drilling results by the Company and its consulting geologist suggests the existence of a high grade gold
zone that coincides with the recently identified structure that controls both geometry and the overall NE-SW trend of the Oculto
deposit. Additional drilling is recommended to test the extent of the high grade gold zone as additional high grade gold in
the eastern portion of the Oculto deposit could result in an increased mine life.
Satellite deposits to Oculto - namely Fantasma, Laderas, and Cerro Viejo - are known to contain silver and/or
gold mineralization near surface. Additional drilling of these deposits may provide additional mill feed to increase the mine
life envisioned in the PEA.
Technical Disclosure
The scientific and technical information in this news release with respect to the PEA has been reviewed and approved by Scott Ladd,
P.Eng. and David Rennie, P.Eng. of RPA, and Gerry Neeling, FAusIMM of GRES, each of whom is an independent "qualified person" under
National Instrument 43-101 – Standards of Disclosure for Mineral Projects ("NI-43-101"). All other scientific and technical
information in this news release has been approved by Willem Fuchter, PhD P.Geo., President & CEO of AbraPlata Resource Corp and a
qualified person as defined by National Instrument 43-101.
A new technical report summarizing the PEA will be filed on SEDAR (www.sedar.com) within 45 days of this news
release.
About AbraPlata
AbraPlata is a junior mining exploration company focused on delivering shareholder returns by unlocking mineral value in
Argentina. The Company's experienced management team has assembled an outstanding portfolio of gold, silver and copper
exploration assets, and is focused on advancing its flagship Diablillos silver-gold property, with an Indicated Mineral Resource
containing 80.9M oz Ag and 732k oz Au, through the various stages of feasibility. In addition, AbraPlata owns the highly
prospective Cerro Amarillo property with its cluster of five mineralized Cu-(Mo-Au) porphyry intrusions located in a mining camp
hosting the behemoth El Teniente, Los Bronces, and Los Pelambres porphyry Cu-Mo deposits. Further exploration work is also planned
for the Company’s Samenta porphyry Cu-Mo property south of First Quantum’s TacaTaca project as well as its Aguas Perdidas Au-Ag
epithermal property.
About RPA
RPA is a global mining consultant with offices in Canada, the United States, and the United Kingdom. The company provides services
to the mining industry at all stages of project development from exploration and resource evaluation through scoping,
prefeasibility and feasibility studies, financing, permitting, construction, operation, closure and rehabilitation. RPA advises
major mining companies, mid-cap producers, junior mining and exploration companies, financial institutions, governments, law firms,
and individual investors on the technical and commercial aspects of mineral property development.
About GRES
GR Engineering Services Limited is a medium-sized, ASX-listed (ASX: GNG) process design and engineering contractor specializing in
providing engineering design and construction services to the mineral processing industry. Headquartered in Perth, Western
Australia, GRES has successfully delivered EPC fixed price projects and EPCM services into a large number of projects which have
been located in many different countries and regions. GRES has teams of highly experienced technical and engineering professionals
and broad experience in the compilation of feasibility studies.
ON BEHALF OF THE BOARD
ABRAPLATA RESOURCE CORP.
"Willem Fuchter"
Willem Fuchter
President & Chief Executive Officer
For further information concerning this news release, please contact:
Willem Fuchter - President & CEO Rob Bruggeman - Investor Relations
Tel: +54.11.5258.0920 Tel:
+1.416.884.3556
E-mail: willem@abraplata.com Email: rob@abraplata.com
This news release includes certain "forward-looking statements" under applicable Canadian securities
legislation. Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered
reasonable, are subject to known and unknown risks, uncertainties, and other factors which may cause the actual results and future
events to differ materially from those expressed or implied by such forward-looking statements. All statements that address future
plans, activities, events or developments that the Company believes, expects or anticipates will or may occur are forward-looking
information. There can be no assurance that such statements will prove to be accurate, as actual results and future events could
differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on
forward-looking statements. The Company disclaims any intention or obligation to update or revise any forward-looking statements,
whether as a result of new information, future events or otherwise, except as required by law.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
For further information about AbraPlata and its projects, please visit the Company’s website at www.abraplata.com.
Photos accompanying this announcement are available at:
http://www.globenewswire.com/NewsRoom/AttachmentNg/218dc95f-806a-428e-a298-f71d6419d57a
http://www.globenewswire.com/NewsRoom/AttachmentNg/7ed8d2cf-b910-43d6-83ac-d8d628fbb428
http://www.globenewswire.com/NewsRoom/AttachmentNg/d527339a-f91a-419c-9c26-16714cf080c6