RE: NewsIt is encouraging that they fixed the problem that caused the 7 day delay. Also that they put in a procedure to prevent this from happening again. That sound like planned maintenance program. If that had not happened then there would have been another 1750 oz. They should have exceeded planned production by a 1000 oz
(2000 ton/day X 96.2%recovery X 3.62 oz/ton X 7 days )
___________________________________ = 1750 oz
28 Grams /oz
1750 OZ missed opportunity + 20272 produced = 22022 potential
This should be enough for this to go in the right direction.