A Schedule
A Schedule I would like to see AVR produce someting like New Gold has done for the commissioning of their New Afton mine. Modified to suit the situation of course.
All the best
CB
2012 Milestones
April - SAG and Ball Mill 'dry commissioning' to commence
End of May - ~900,000 tonnes of ore stockpiled on surface
June - First ore through mill
End of June -26 drawbells developed to support 6,600 tonne per day mining rate
July - First concentrate shipment
July - Achieve mining rate of 6,600 tonnes per day compared to current ~3,000 tonnes per day
August - Achieve commercial production of 6,600 tonnes per day processed
September - Start utilizing gyratory crusher thus enabling mining rate to move towards design capacity of 11,000 tonnes per day
October - Mill to reach design capacity of 11,000 tonnes per day
End of December - Complete a total of 48 drawbells to support 11,000 tonne per day mining rate