RE:Take the short cut" 550 pounds per hour " does not mean that a 550-pound batch has to be done in one hour.
We know there are 4 stages in the process: reactor A, reactor B, separation, extraction.
When every stage takes one hour or less, the " 2.5 ton per day per module " is achieved in a continous opperation. ( In case either reactor A or B needs more time, let's say 2 hours, the team just has to add another reactor. )
AT.