Absolute failure
We need to face the facts. This has been an absolute failure. Nothing that management claimed actually came true.
Remember when the factory was going to generate $15M per year in profits? Remember when the factory was going to produce 70k ounces of platinum per year? Remember when module 1 was going to be in full production by July 2023, and then by October 2023? Remember when the factory had a grand opening? Remember when "the commissioning process will take approximately 90 days to go from 1 pound a day of throughput to get to 2.5 tons per day of throughput for module 1"? Remember when all we needed was to heat the process with a boiler? Remember when the gas line was not big enough to run the boiler? Remember when all we needed was to fix the stirring mechanism?