RE: SOCO Secures Rig
RE: SOCO Secures RigEach well is expected to take 40-50 days to drill and another 2-3 weeks/well if testing is required.
Its expected they will spud in mid July.It could take 5-7 months to complete the drilling.
According to Energulfs plans they expect to complete the seismic in Lotshi in July.
If they fast track the post seismic work its not out of the question that Energulf could take over the rig.