RE:Production From May news release.....Open pit mining is planned to gradually resume in July 2020. During the period from July to December 2020, an estimated 1.7 million to 1.9 million tonnes of ore are scheduled to be placed on the leach pad with an average gold grade of 1.00 g/t to 1.10 g/t. The estimated stripping ratio during this period is 0.68 to 0.75.
Between 25,000 to 28,000 ounces of gold dor are scheduled to be produced for the period of September to December 31, 2020. Commercial production is expected to start in the first quarter of 2021,