CALGARY, ALBERTA--(Marketwired - July 15, 2013) - Mart Resources, Inc. (TSX VENTURE:MMT) ("Mart" or the "Company") and its co-venturers, Midwestern Oil and Gas Company Plc. (Operator of the Umusadege field) and SunTrust Oil Company Limited are providing the following update on Umusadege field production for June 2013.
June 2013 Production Update
Umusadege field production during June 2013 averaged 10,700 bopd. Umusadege field downtime during June 2013 was approximately 4 days due mainly to maintenance and repairs on the export pipeline performed by the pipeline operator. The average field production based on producing days was 12,500 bopd in June 2013.
Total net crude oil deliveries into the export pipeline from the Umusadege field for June 2013 were approximately 305,100 bbls before pipeline losses. Pipeline and export facility losses for May 2013 and for June 2013 have not yet been reported by the pipeline operator.