Rio Alto Produces 48,427 Ounces of Gold in Q2 2013 Rio Alto Produces
Rio Alto Produces 48,427 Ounces of Gold in Q2 2013
07:00 EDT Thursday, July 11, 2013
VANCOUVER, BRITISH COLUMBIA--(Marketwired - July 11, 2013) -Rio Alto Mining Limited ("Rio Alto") (TSX:RIO)(NYSE:RIOM)(LMA:RIO)(DBFrankfurt:MS2) is pleased to announce that its La Arena Gold Mine produced and sold 48,427 ounces of gold during the three months ended June 30, 2013, 4,822 ounces more than planned for the period (84,783 ounces of gold poured for the six months ended June 30, 2013 compared to 78,553 ounces planned for the period).
Ore and waste production from the La Arena Gold Mine for the second quarter of 2013 was:
|
Actual |
Planned |
Difference |
|
Tonnes |
Au gpt |
Tonnes |
Au gpt |
Tonnes/Ozs |
|
Au gpt |
|
|
|
|
|
|
|
|
Ore mined |
3,001,082 |
0.647 |
3,536,000 |
0.470 |
(534,918 |
) |
0.166 |
Waste mined |
6,242,967 |
|
5,923,000 |
|
319,967 |
|
|
|
|
|
|
|
|
|
|
Ounces poured |
48,427 |
|
43,605 |
|
4,822 |
|
|
Production for the first six months of 2013 amounted to:
|
Actual |
Planned |
Difference |
|
Tonnes |
Au gpt |
Tonnes |
Au gpt |
Tonnes/Ozs |
|
Au gpt |
|
|
|
|
|
|
|
|
Ore mined |
5,285,268 |
0.587 |
5,712,000 |
0.481 |
(426,732 |
) |
0.106 |
Waste mined |
12,237,993 |
|
12,048,000 |
|
189,993 |
|
|
|
|
|
|
|
|
|
|
Ounces poured |
84,783 |
|
78,553 |
|
6,230 |
|
|
Gold production exceeded plan for both the first and second quarters of the year due to better than expected ore grade of 0.647 gpt for Q2 compared to planned grade of 0.470 gpt (0.587 gpt realized compared with 0.481 gpt planned for the six months ended June 30, 2013). Management reaffirms its production guidance of 190,000 to 210,000 ounces of gold production for calendar 2013.
As part of its 2013 operational strategy, the Company continues to optimize its mining activities at La Arena and management believes that, irrespective of the recent falls in the gold price, its mining operations will continue to generate strong positive cash flows.
The search for COO is in process with an appointment expected before year end. In the meantime, President & CEO, Alex Black, has assumed the role and responsibilities as COO.
Permitting for the La Arena Phase II project is underway and a feasibility study for the project is scheduled to be completed by the end of Q1 2014. The Company had originally planned to fund Phase II with cash flow from its gold oxide mining operations. As a consequence of the recent drop in metal prices and the need to conserve existing cash reserves, the Company has decided to evaluate alternative sources of funding.
Rio Alto will release its Q2 financial results on August 13, 2013
of Gold in Q2 2013
07:00 EDT Thursday, July 11, 2013
VANCOUVER, BRITISH COLUMBIA--(Marketwired - July 11, 2013) -Rio Alto Mining Limited ("Rio Alto") (TSX:RIO)(NYSE:RIOM)(LMA:RIO)(DBFrankfurt:MS2) is pleased to announce that its La Arena Gold Mine produced and sold 48,427 ounces of gold during the three months ended June 30, 2013, 4,822 ounces more than planned for the period (84,783 ounces of gold poured for the six months ended June 30, 2013 compared to 78,553 ounces planned for the period).
Ore and waste production from the La Arena Gold Mine for the second quarter of 2013 was:
|
Actual |
Planned |
Difference |
|
Tonnes |
Au gpt |
Tonnes |
Au gpt |
Tonnes/Ozs |
|
Au gpt |
|
|
|
|
|
|
|
|
Ore mined |
3,001,082 |
0.647 |
3,536,000 |
0.470 |
(534,918 |
) |
0.166 |
Waste mined |
6,242,967 |
|
5,923,000 |
|
319,967 |
|
|
|
|
|
|
|
|
|
|
Ounces poured |
48,427 |
|
43,605 |
|
4,822 |
|
|
Production for the first six months of 2013 amounted to:
|
Actual |
Planned |
Difference |
|
Tonnes |
Au gpt |
Tonnes |
Au gpt |
Tonnes/Ozs |
|
Au gpt |
|
|
|
|
|
|
|
|
Ore mined |
5,285,268 |
0.587 |
5,712,000 |
0.481 |
(426,732 |
) |
0.106 |
Waste mined |
12,237,993 |
|
12,048,000 |
|
189,993 |
|
|
|
|
|
|
|
|
|
|
Ounces poured |
84,783 |
|
78,553 |
|
6,230 |
|
|
Gold production exceeded plan for both the first and second quarters of the year due to better than expected ore grade of 0.647 gpt for Q2 compared to planned grade of 0.470 gpt (0.587 gpt realized compared with 0.481 gpt planned for the six months ended June 30, 2013). Management reaffirms its production guidance of 190,000 to 210,000 ounces of gold production for calendar 2013.
As part of its 2013 operational strategy, the Company continues to optimize its mining activities at La Arena and management believes that, irrespective of the recent falls in the gold price, its mining operations will continue to generate strong positive cash flows.
The search for COO is in process with an appointment expected before year end. In the meantime, President & CEO, Alex Black, has assumed the role and responsibilities as COO.
Permitting for the La Arena Phase II project is underway and a feasibility study for the project is scheduled to be completed by the end of Q1 2014. The Company had originally planned to fund Phase II with cash flow from its gold oxide mining operations. As a consequence of the recent drop in metal prices and the need to conserve existing cash reserves, the Company has decided to evaluate alternative sources of funding.
Rio Alto will release its Q2 financial results on August 13, 2013