Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Quote  |  Bullboard  |  News  |  Opinion  |  Profile  |  Peers  |  Filings  |  Financials  |  Options  |  Price History  |  Ratios  |  Ownership  |  Insiders  |  Valuation

Atkinsrealis Group Inc T.ATRL

Alternate Symbol(s):  SNCAF

SNC-Lavalin Group Inc. is a fully integrated professional services and project management company. The Company connects people, technology and data to help shape and deliver concepts and projects, while offering comprehensive solutions across the asset lifecycle. Its segments include Engineering Services; Nuclear; O&M; Linxon; LSTK Projects, and Capital. The Engineering Services segment includes consultancy, engineering, design and project management services. The Nuclear segment supports clients across the entire nuclear lifecycle with the full spectrum of services from consultancy, EPCM services, field services, technology services, spare parts, reactor support and decommissioning and waste management. The O&M segment consists of providing operations, maintenance and asset management solutions. The Linxon segment offers engineering, procurement, management and construction services. The LSTK Projects is comprised of the remaining LSTK construction contracts of the Company.


TSX:ATRL - Post by User

Post by domjoy80on Nov 12, 2021 8:48am
110 Views
Post# 34118738

REM: où en sommes-nous?

REM: où en sommes-nous?https://www.lesaffaires.com/dossier/infrastructures-et-grands-projets/rem-ou-en-sommes-nous-/627984

En plus de decaler les dates de livraison de 9 a 18 mois selon les secteurs, ces differents imponderables ont fait monter la facture, qui est passee de 6,3 G$ a 6,9 G$. « Les differents risques de construction et de depassement de couts sont tous assumes par CDPQ Infra », precise le porte-parole. Depuis 2015, cette filiale de la Caisse de depot et placement du Quebec se devoue aux projets d’infrastructure.

Pour l'instant, SNC (le consortium) assume une grande partie de ces couts. Est-ce que c'est ca?
Si oui, il y aura donc eventuellement une bon retour $$$ dans les coffres.