RE:PFS announcedNext step financing for the $30 million + to ready mine/mill for production, which requires a few months.
They have to start running by Nov 2018 to meet the completion test by 12/31/19 of 400 tons/day for 30 days (or renegotiate streaming agreement). Failure to complete the test requires about 9 million dollar payment to Wheaton, subject to adjustment proportional to test results achieved.
Production was suspended in 2013; this could be the startup year.