Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.

Euro Sun Mining Inc T.ESM

Alternate Symbol(s):  CPNFF

Euro Sun Mining Inc. is a Canada-based mining company focused on exploration of gold and copper. The Company is focused primarily on its 100% owned Rovina Valley Project (RVP) located in west-central Romania. The Company operates through the development of its Romanian mining permit segment. The Rovina Valley Project consists of three copper-gold porphyry systems, such as Rovina, Colnic and Ciresata. The Company’s wholly owned subsidiaries include SAMAX Romania Limited and SAMAX Romania S.R.L.


TSX:ESM - Post by User

Bullboard Posts
Post by urai58on Apr 13, 2019 8:55am
53 Views
Post# 29622427

Approval process for Colnic: 13 steps, about 3 years

Approval process for Colnic: 13 steps, about 3 yearsUntil the start of production, Euro Sun Mining has to work 13 steps in the approval process. I have posted this before.
  1. General Urbanization Plan (“PUG”): land use approval for new categories on a local and regional area basis (includes public meetings for feedback and approval).
     
  2. Zonal Urbanization Plan (“PUZ”): land use approval for industrial zones including detailed development plans (includes public meetings for feedback and approval).
     
  3. Environmental procedure requirements through local environmental protection agency
     
  4. Approval by the local County Council.
     
  5. Environmental License.
     
  6. Environmental and Social Impact Assessment approval (“ESIA”)
     
  7. Closure and Remediation plan
     
  8. Technical Authorization Committee (“TAC”) approval. The TAC is comprised of experts and interested parties from recognized institutions.
     
  9. Public hearings for feedback.
     
  10. TAC and company review of public feedback (as per the Equator Principles).
     
  11. Approval from the Regional Environmental Agency.
     
  12. Contruction Permit issuance, allows construction to begin.
     
  13. Operational License.
 
At least 2 years plus 1 romanian year (post-communist bureaucracy with apparatchiks.
 
 