They started putting the steel up on August 18 per August 16 press release , i have to think that pic is 2 weeks old at least !!!! The water treatnment plant should be done by now and the interior should be moving along at break neck speed , i see the fuel island is also done [ hey the contractor must have done two things at the same time ] . I would think the crusher mill site concret work should be progressing at this time as the contractor that did the water treatnment plant hinted that he also had that contract .
The company has said as soon as the water treatnment plant was up and running we could go underground and this should happen in a few weeks .
Now for that big picture , i did a simple cut & past and that is how it came out .
LOL