RE:Missing linkAccording to the latest MDA's, CC, and the 01/11/18 NR:
Red Chris: commenced mining the deeper high-grade material in the pit in late Q3 2017 but will return to the pushback of lower grade, low recovery, high clay ore in H2 2018. The 5 Huckleberry trucks will enable RC to increase the mining rate to open up and mine the deeper zone of the pit. So expect a good H1 but an ugly H2 2018.
Mount Polley: mining of the Cariboo pit will be completed in mid-2018 and development of the Springer pit will be completed by (early?) 2019. So only the low-grade stockpile will be milled in H2 2018. So expect a good H1 but an ugly H2 2018.
Brian Kynoch stated during the CC that the updated mine plans (already disclosed to the lenders and the insider shareholders) will be disclosed to all shareholders in early 2018. Still waiting ...