ceetong wrote: The official wording now is "...commissioning to be completed by the end of Q1 2023." I bet my sweet bippy this is not going to hold and we will be lucky if we see the system being commissioned in Q2-2023.
Well, less than a month later we have bean dealt ANOTHER delay. The wording now is "[we] now expect the completion of the commissioning of the EGPE VRFB to be pushed into Q2
2023."
Until futher notice!