Quick update on wellfield injection timelineHad a short exchange with JJ regarding wet commissioning status, the start of acid injection, and whether the two were related in some way (did receipt of the injection permit depend on the commissioning process and anything they may have found). JJ said he expects the injection permit by the middle of November and that the EPA is basically checking the boxes on what MIN has done and what's on the permit, no relationship between the commissioning itself and the permit. Also, there have been no issues with the commissioning process and everything is "ready to go".
I did not ask explicitly, but see no reason why acid injection would not start immediately upon receipt of the final permit.
GTLA