RE:RE:Following the crumbs
LKAB has six pelletizing plants: three in Kiruna, two in Malmberget and one in Svappavaara. The total capacity of the plants amounts to approximately 28 million tonnes of processed iron ore products per year
That makes for a possible 300 plasma torches.
Customer A in the news release of May 19 has more than 10 plants requiring 50 torches each, which makes for 500 torches
Customer B, In the news release of last Friday requires 100 torches or 2 plants.
But in the March 4 release about successful completion of the work with Rise/LKAB it was mentioned that:
'these tests have concluded successfully, and discussions are now taking place for follow on work and additional torch orders'
Customer B is a new customer beside Rise/LKAB? I would think so since there was never any confidentiality claim associated with any of the releases made by Pyrogenesis with regard to RISE/LKAB