Pilot plant update...I got this response from AMY the same day I sent my query about the reporting process for the latest news release in relation to the pilot plant....
Thank you for your email and investment into AMY.
I would like to clarify that the Pilot Plant is planned to run at 1kg/hr on a continuous basis. However, our approach on getting the Pilot Plant to run on a continuous basis is to first construct and test in stages. For instance, there is the pre-treatment stage where we separate the active material from the aluminum foil, followed by leaching and precipitation stages etc.
AMY will look to analyze and report on the development of each stage prior to full operation. From my experience, once the Pilot Plant is fully operational we will be able to increase processing rates up to 10kg/hr.
I hope this answers your questions and please feel free to reach out at any time.
Best regards,
Zarko Meseldzija
Chief Technical Officer | American Manganese Inc.
phone: +1 778 574 4444
mobile: +1 778 237 5585
site: www.americanmanganeseinc.com
email: zmeseldzija@amymn.com
They are on the right track with a well thought out plan, plenty of news coming on many fronts...looking forward to a great finish to 2018! Best of luck KF12