When you do your DD you will come to realityI was bored and looked at Bontera's new plan to see how much time I have before I get back in...to my surprise ...OUCH!!!
Mill permitting was due in new year with construction to begin with pre-production end of Q4...
NOW PERMITING FOR MILL EXPECTED BY END OF 2023 MEANING MILL WON'T BE READY TILL Q3 2024 after contruction
Barry open pit PFS, including updated MRE under review now middle Q3 2023...
Barry underground...
technical review till the end of 2024...
Barry surface drilling till July 2024
Barry underground drilling starting in 2024 through to 2025 for definition drilling 15,000- 25,000 meters
Barry underground PEA end Q2 2024 , but pending on drill results...
Barry underground developement and bulk sample end of 2024 maybe 2025
GLADIATOR
RAMP PERMITTING END OF 2024
Glasiator no drilling in 2023 expect 5,000 meters to begin undergroung Aug 2024...
Barry & Gladiator access road or linking , permitting end of 2023 and construction by end of 2024...
Bottom line Bontera ain't producing gold till maybe END OF 2024...therefore all this work will require capital ..and it's sad to have to raise money at these low prices...
AFTER DOING MY DD ...I HAVE TIME...SORRY FOR THOSE WHO GOT PUMPED..A TAX LOSS MY BE A SMART MOVE FOR MANY HERE ...YOU NEED TO BE OUT FOR 30 DATS BEFORE YOU GET BACK IN...CAN'T BEAT MINING KNOWLEDGE ...GLTA