Expect news any day now This is an excerpt from their recent April 30 MD&A
CURRENT COMPANY ACTIVITY
The first carbon strip and resulting gold pour is scheduled for completion the first week of May. The
Company has employed the assistance of the carbon-stripping vendor, Kappes Cassiday & Associates,
for the commissioning of this system.
Mining operations are ongoing at site. The adoption of leaching has converted the mill to a zero discharge
facility. Commissioning this system has resulted in minor shutdowns to milling operations.
The mine has its largest ever inventory of broken ore, with approximately 8,000 tonnes total underground and on surface which grade approximately 17 g/t. An additional 4,600 tonnes of similar grade will be blasted before the end of May 2012