RE: Mako TD approx July 8I noted Dr Szabo saying 10ft/hr in the conference call
but in fact since the conference call of April 26 they
have April 26 = 4846m to May 16 = 5146m that is 300m in
19 days or about 16m/day = 52.5 ft/day nowhere near 10ft/hour
about 2.2 ft/hr
Based on this rate of drilling TD on Mako 1 about July 8 not June,
Mako 1 and Mako2 drilling is by Crosco 801
Do we know where the other rig Crosco 403 is going ?, it has completed 2 holes, but where does it go now and what is the name of the new hole, I assume that there will be more holes from this rig
as theknight reports "Up to 5 holes will be drilled by the end of the July and testing of the wells will begin around that time(and maybe a little before)"
That will mean that Crosco 403 will have to drill 2 holes between now
and end of July which is possible if they are similar to the holes
that they have been drilling eg around the edge of the formation.
Just wondering where they are and what they are called
All the best