115274 oz High Grade Silver produced in 2 month Hunt Mining Completes Third Delivery of Concentrate and Production Summary
LIBERTY LAKE, WASHINGTON--(Marketwired - April 18, 2017) - Hunt Mining Corp. ("Hunt" or the "Corporation") (TSX VENTURE:HMX) is pleased to announce the third delivery of concentrate from production activities at the Martha Mine Project ("Martha Project") to the port. To date, the Corporation has completed three (3) deliveries from the Martha Project consisting of the following amounts:
Production Summary of Concentrate from Martha Project
Delivery | Dry Weight (kg) | Ag g/t (weighted average) | Au g/t (weighted average) | Ag ounces (troy ounces) | Au ounces (troy ounces) |
March 7, 2017 | 17,612 | 55,687 | 47.90 | 31,532 | 27 |
March 29, 2017 | 16,835 | 76,184 | 74.30 | 41,235 | 40 |
April 18, 2017 | 16,666 | 79,330 | 91.17 | 42,507 | 49 |
Total | 51,113 | | | 115,274 | 116 |
https://web.tmxmoney.com/article.php?newsid=7701889983926114&qm_symbol=HMX