RE: Patrick email + Mining Lease? thx for clearing that topic aurifier.
It is nice to see that we got approval from CTPAQ!! Next steps are following for the Mining Lease
- A mine Closure Plan must be submitted to the MRNF: Closure Plan: A Preliminary Closure Plan was prepared by Genivar and submitted to the MRNF and the MDDEP (Ministère du Développement durable, de l'Environnement et des Parcs) for approval. Based on the closure plan, the financial guarantee requested has been estimated at $95,757, which reflects the relatively benign nature of a placer gold mining operation.
A final Closure Plan must be filed prior to the commencement of mining operations. A financial guarantee of $95,757 must be provided to the MRNF by the company's to cover rehabilitation obligations under the CP as part of the final filing process.
- A Geological Report must be submitted to the MRNF, the Technical Report will need to detail the geology and the economic potential of the Beauce placer gold deposit. Geological Report: Inlandsis Consultants has completed the required technical report and it will be submitted to the MRNF shortly.
Do we know if the final Closure Plan has been sent to MRNF and has the guarantee been covered?
I assume that the geological report has already been sent.
It is getting exciting here :)