News Release today... From today's News Release
'A total of 61,404 metres have been drilled to date out of the planned 100,000 metre program. Assays are pending for samples from approximately 4,263 metres of core (11.4% of the total submitted).
The Company has $20 million in cash and is well funded to carry out the remaining 39,000 metres of the planned drill program as well as further exploration to add to the pipeline of drill targets on the property.'
Results have been less than impressive to date, but they still have a lot
of drilling to do and assays to receive.