RE:RE:Happy Easter Sunday! We have received all permitting to complete our exploration work comprising drilling. Mechanical trenching stripping etc.through MNDM.
The permit for the Advanced Exploration Permit is well in progress and we are finalizing the engineering component for reequipping the shaft. All base baseline environmental studies have been completed.
We still have a lot of drilling to complete in the shaft area to bring it to proven/probable resources, so we anticipate we will have the Advanced Exploration Permit in place as we are aware of the lengthy government approvals, hence we commenced this permitting application well in advance.