RE:Repost of Kentors Update on Heap leaching MurchisonNow the questions is: With purchase of Kentor's assets in Murchison deal,did that also include material for the "heap leach plant"? If it was included, what shape is it today? ..... Richard
Ref: https://www.asx.com.au/asxpdf/20120703/pdf/4276ckq7kj5lmk.pdf
Page 3 of 7
Kentor Gold purchased a complete heap leaching circuit from the Indee gold project last year for $1.1m. This equipment has been dismantled and transported to the Murchison Gold Project site in preparation for construction of a heap leach operation. The gold room, stripping plant and RO plant from Indee have already been installed in the Burnakura CIL gold plant. This installation has more than enough excess capacity to strip additional loaded carbon from the heap leach operation"
Table 2 Capital Cost Estimate Heap Leach
Capital Cost $ Refurbishment and New Equipment $ 2,300,000 Installation of Equipment $ 2,400,000
EPCM $ 450,000
Other Directs $ 100,000
Indirects $ 50,000
Initial Pad and Pond Construction $ 2,000,000
Contingency $ 200,000
Total Estimate $ 7,500,000
This was back in July 03, 2012