RE: Guestimated drilling scheduleCabrio, I think you're off on a couple wells.
Murphy has likely already spud their second well in January, should be completed sometime before end of February.
Inpex will take the rig after Murphy and they will have to hand over the rig before end of May to Repsol. According to the work commitment aggreement for the Georgetown block, Repsol must spud before end of May.
Jaguar is a deep well and will take six (6) months to drill according to Repsol, so it will not be completed in August. More likely October/November. And Eagle will follow if they use the same rig which has to be spud before end of December according to the work commitment for Corentyne.
Also, a well will be spud in Feb off the coast of French Guiana, operated by Shell/Tullow. It's in the deep waters.