RE:RE:RE:COR LetterWhat justification or evidence is there that this upgrade is dedicated for Sugarbud to source power? What evidence is there that the building is not connected to the grid at this time?
You are siting a project application by the AESO to the utilities commission for an upgrade in capacity to reliably serve the Stavely area for long anticipated load growth in the area. This application is a result of a request by Fortis and connection reliability assessment package that had been completed by engineering in 2017. This has been years in the making.
Site more sources or reasoning.
https://www.aeso.ca/assets/Uploads/Appendix-A-Connection-Assessment-Vulcan-and-Stavley.pdf