Enbridge completes 14 km pipeline to our neighbors new mine. Greenstone Mine wishes to advise the public that open pit activities are underway. Greenstone Mine will be conducting scheduled blasts within the Open Pit. Blasting Notices are posted on the website homepage.
Work continues on the retaining wall (MSE Wall) by the Crusher. At the Power Plant, work on the outside auxiliary systems is ongoing. The gensets continue to arrive at site. Interior work in the Truck Shop is ongoing with the installation of overhead doors ongoing. Formwork and concrete for conveyors is ongoing. Power distribution work continues in the Plant Site and Tailings Management Facility (TMF) areas.
Enbridge has completed the installation of the 14 km pipeline to the Project site and final clean up continues. Installation of the two metering stations is well advanced.
Mine mobile equipment components continue to arrive. Assembly of the first four mine haul trucks and shovel is complete. Assembly of the second shovel at the assembly pad area continues. The construction of haul roads continues.
Construction in and around Greenstone Mine involves the use of heavy equipment such as haul trucks, zoom booms, cranes, drills, excavators, skidders, wood chippers, bulldozers, tri-axle haul trucks, articulated trucks and loaders. For health and safety reasons, do not enter any unauthorized or active work areas within the Project footprint unless authorized to do so.