Permitting Process p 18 - Feb 2017 Presentation
https://media.wix.com/ugd/5d173e_471f8352b6124daf9da0ec17bf7d975c.pdf
The permitting and authorization process for the Silicon Ridge Project will consist mainly of three separate ministries awarding permits, authorizations and certificates, including:
A. The Ministre des Forts, de la Faune et des Parcs (the “MFFP”, Ministry for Forestry, Wildlife and Parks) which issues an authorization under section 128.7 of the Act Respecting the Conservation and Development of Wildlife (a “Sec 128.7”); in parallel to this, Rogue is applying to,
B. The Ministre de l'nergie et des Ressources naturelles (the “MERN”, Ministry for Energy and Natural Resources) for a bail d’exploitation minire permit (also known as a “BEX permit”);
these two approvals will lead to,
C. The Ministre du Dveloppement durable, de l’Environnement et de la Lutte contre les changements climatiques (the “MDDELCC”, Ministry for Sustainable Development, Environment and Climate Change) which grants the Certificate of Authorization (a “CofA”). As outlined in the 2017 Plan, Rogue and SNC-Lavalin understand this process will culminate with the CofA, expected in the summer.