Metallurgical Drill Hole Results, BishaNevsun Resources Ltd.: Metallurgical Drill Hole Results, Bisha, Eritrea
VANCOUVER, BRITISH COLUMBIA, Feb 2, 2006 (CCNMatthews via COMTEX) --
Nevsun Resources Ltd. (TSX:NSU)(AMEX:NSU) ("The Company") is pleased to announce the results of assaying from drill holes specifically put down to obtain a bulk sample for metallurgical purposes. The drill program took part in two phases in 2005. Although preliminary test results having been recently released in the Bisha Scoping Study carried out by AMEC Americas Limited, additional metallurgical test work will be completed in conjunction with the Bisha Feasibility Study currently being completed. Metallurgical test work for both the Scoping Study and the Feasibility Study is being carried out at SGS Lakefield.
Metallurgical Drill Hole AssaysA summary of significant assay intervals follows:---------------------------------------------------------------------Hole # Domain From To Meters Au g/t Ag g/t % Cu % Zn---------------------------------------------------------------------Met-05-01 oxide 30.0 36.0 6.0 8.15 94.20 - ---------------------------------------------------------------------- supergene 42.0 68.5 26.5 - - 2.11 ---------------------------------------------------------------------- primary 67.5 157.5 90.0 - - 1.33 5.53--------------------------------------------------------------------- primary 157.5 202.5 45.0 - - 1.07 1.13---------------------------------------------------------------------Met-05-02 supergene 55.5 70.0 14.5 - - 0.46 1.27--------------------------------------------------------------------- primary 70.0 112.0 42.0 - - 0.35 1.75--------------------------------------------------------------------- primary 175.7 247.0 71.3 - - 0.71 9.24--------------------------------------------------------------------- primary 247.0 255.4 8.4 - - 0.92 3.00---------------------------------------------------------------------Met-05-03 oxide 3.0 33.0 30.0 6.09 - - ---------------------------------------------------------------------- supergene 40.5 82.5 42.0 - - 4.41 ---------------------------------------------------------------------- primary 82.5 123.3 40.8 - - 0.02 1.12---------------------------------------------------------------------Met-05-04 oxide 0.0 36.0 36.0 3.36 - - ---------------------------------------------------------------------- supergene 40.5 84.0 43.5 - - 1.23 ----------------------------------------------------------------------Met-05-05 supergene 34.5 50.5 16.0 - - 9.04 ---------------------------------------------------------------------- primary 50.5 109.0 58.5 - - 2.29 7.31--------------------------------------------------------------------- primary 109.0 115.0 6.0 - - 2.15 2.00---------------------------------------------------------------------Met-05-06 oxide 22.0 34.5 12.5 3.18 19.80 - ---------------------------------------------------------------------- supergene 34.5 62.5 28.0 - - 9.14 ---------------------------------------------------------------------- primary 62.5 89.5 27.0 - - 1.95 7.04--------------------------------------------------------------------- primary 89.5 125.0 35.5 - - 2.16 1.96--------------------------------------------------------------------- Stringer--------------------------------------------------------------------- sulphides 125.0 145.0 20.0 - - 0.69 0.27---------------------------------------------------------------------Met-05-07 oxide 31.5 42.0 10.5 5.48 6.64 - ---------------------------------------------------------------------- supergene 42.0 68.5 26.5 - - 2.11 ---------------------------------------------------------------------- primary 68.5 124.3 55.8 - - 0.46 4.09---------------------------------------------------------------------Met-05-08 supergene 40.5 58.8 18.3 - - 16.40 ----------------------------------------------------------------------
Not all intervals were assayed for all elements on a sample by sample basis. Composite samples were subsequently assayed for multiple elements. Drill holes using PQ and HQ sized core were located in areas where it was thought samples representative of the various phases of the deposit could be obtained. The holes were not necessarily designed to cross-cut the mineralized trend at right angles but more to obtain adequate quantities of material to make up various composite samples that reflected the three major metallurgical domains that make up the Bisha deposit. See Figure 1 for drill hole locations.
Bill Nielsen, P.Geo. and Nevsun's Vice-President of Exploration, the qualified person under National Instrument 43-101, supervised and directed all work associated with the drilling program.
The Bisha Scoping Study indicated recoveries of 87% for the gold in the Oxide layer, 85% for copper in the Supergene copper layer, and concentrate recoveries of 83% copper and 85% zinc for the Primary massive sulphides.
--------------------------------------------------------------------- Tonnes Au Ag Cu Zn Au Ag CuOre m g/t g/t % % recovery recovery recovery---------------------------------------------------------------------Oxide 4.1 7.6 35.8 0.1 0.1 87% 45%---------------------------------------------------------------------Supergene Cu 6.3 1.0 41.1 4.1 0.5 42% 64% 85%---------------------------------------------------------------------Primary 3.1 0.7 36.2 1.4 1.8 Concentrate recoveries are: 83% copper and 85% zinc---------------------------------------------------------------------Primary Zn 7.0 0.8 59.2 1.2 9.4---------------------------------------------------------------------Total tonnes 20.5--------------------
Bisha Project Update
The robust economic results of the Bisha Scoping Study, completed by AMEC Americas Limited, were released on December 9th, 2005. A 43-101 Technical Report and Preliminary Assessment for the Bisha Project was filed on December 30, 2005 and can be viewed on www.nevsun.com.
The pre-tax and pre-financing project economics as presented in the scoping study are shown below.
Bisha Project Economics-------------------------------------------------------------------- 0%Economic Commodity Discount PaybackScenarios Price Scenario NPV IRR Period--------------------------------------------------------------------Current Commodity Gold US$ 495/oz US$ 1.3 B 71% 1.3 years Prices (Nov 30/05) Copper US$ 1.99/lb Silver US$ 8.27/oz Zinc US$ 0.76/lb--------------------------------------------------------------------Conservative Gold US$ 400/oz US$ 346 M 35% 1.9 years Historical Copper US$ 1.05/lb Commodity Prices Silver US$ 6.00/oz(AMEC Base Case) Zinc US$ 0.50/lb--------------------------------------------------------------------
On January 10th, 2006 Nevsun released the 2005 Bisha Resource Statement. The updated independent resource showed higher grades and an increase in metal content in the measured and indicated category; as well as a 100% increase in tonnes in the inferred category. Although the Bisha Scoping Study utilized the 2004 resource statement, the 2005 Bisha Resource Statement will be incorporated into the Final Bisha Feasibility Study that is currently underway.
Forward-Looking Statements: The above contains forward looking statements that are subject to a number of known and unknown risks, uncertainties and other factors that may cause actual results to differ materially from those anticipated in our forward-looking statements. Factors that could case such differences include: changes in world commodity markets, equity markets, costs and supply of materials relevant to the mining industry, change in government and changes to regulations affecting the mining industry. Forward-looking statements in this release include statements regarding the additional resource potential and final feasibility study. Although we believe the expectations reflected in our forward looking statements are reasonable, results may vary, and we cannot guarantee future results, levels of activity, performance or achievements.
NEVSUN RESOURCES LTD.
Dr. John A. Clarke, President & Chief Executive Officer
For further information, Contact:
To view the Bisha Metallurgical Drill Hole Locations attached to this release please click on the following link:
https://www.ccnmatthews.com/docs/0202nsu.jpg
SOURCE: Nevsun Resources Ltd.
Nevsun Resources Ltd. Judy Baker (604) 623-4704 or (416) 786-7860 or 1-888-600-2200 nevsuninfo@nevsun.com www.nevsun.com
Copyright (C) 2006 CCNMatthews. All rights reserved.