Exploration Update 2 JulyMon Jul 3, 2006
Kimberlite Drilling Resumes at Mwadui
--------------------------------------------------------------------------------
Diamond drill hole GHDD-32 at the company's Itetemia Gold Project has reached a depth of 467.5 metres. Total depth is expected to be 580 metres. Should the current drill performance be maintained (June 30 = 31 metres; July 01 = 56 metres; July 02 = 41 metres) the hole could be completed this week.
In the meantime, RC drilling resumed on June 30th at the company'w Mwadui kimberlite project. Three kimberlites are being tested: K1, K2 and K3. A total of 17 holes aggregating 449 metres were drilled in the three day period ending July 03.