Here's all the NEGATIVES again.###### Plumbing and electrical
wiring is nearing completion and one diesel generator remains to be brought on line.
###### Commissioning of each of the individual plant components will commence as soon as the
second generator is operable.
###### Installation of the lining has been
delayed firstly by the insolvency of a previous contractor and secondly by the late
delivery of the HDP liner from Spain. ###### Under the supervision of a second contractor, this
was to have arrived the week of 6th November but now is expected to arrive the week of
13th November. ###### Two dry periods of 3-4 days in duration each are required to line both structures
after the arrival of the lining.
###### Construction progress has suffered from a series of delays, most recently due to specialist
sub-contractors. These have added to delays incurred early in the project due to changes
in mandatory archaeological supervision and ###### difficulties with handling large quantities of
saturated peat. ###### Delays may continue to accrue until
project completion.
###### Work remaining includes installation of the regrind mill and gravity concentration
equipment consisting of a Knelson concentrator and table.
##%%&&**### There are concerns about the ability of the plant to
maintain a high degree of operating time, largely due to lack of duplicates including
pumps. ##%%&&***##