NEWS:Marketwire
URSA Major Minerals Incorporated
October 9, 2007 - 10:33:48 AM
URSA Major Minerals Completes Haulage of 50,000 Tonne Bulk Sample From
Shakespeare Nickel Project to Strathcona Mill, Sudbury Area, Ontario
TORONTO, ONTARIO--(Marketwire - Oct. 9, 2007) -
URSA Major Minerals Incorporated (TSX:UMJ) ("URSA Major") is pleased to
announce that the Company has completed the mining, crushing and haulage of a
50,000 tonne bulk sample from the Shakespeare nickel project. The ore has been
stockpiled at Xstrata Nickel's Strathcona mill and it is anticipated that
Xstrata Nickel will start batch processing the ore during the week of October
15, 2007. The Shakespeare nickel project is located 70 km west of Sudbury,
Ontario.
Richard Sutcliffe, URSA Major's President and CEO stated, "We are very pleased
to have completed this milestone. The bulk sample will provide us with an
important test of the mining characteristics, reserve grade and metallurgical
recoveries at a commercial scale. This will further enable us to advance our
objective of developing a 4,500 tpd mine and mill at the Shakespeare deposit.
Although not intended as a commercial scale operation, URSA Major expects that
the bulk sample will provide significant cash flow." William Day Construction
Limited carried out the excavation, crushing and haulage of the bulk ore
sample from the Shakespeare nickel deposit.
URSA Major completed a positive full feasibility study on the Shakespeare
Project in 2006. The feasibility study is available on the Company's website
at www.ursamajorminerals.com. The Shakespeare deposit contains a diluted
Probable Reserve of 11,226,000 tonnes grading 0.33% nickel, 0.35% copper,
0.02% cobalt, and 0.9 g /t precious metals.
URSA Major is also pleased to announce that Mr. William Dillabough has been
appointed Shakespeare Project Site Manager. Mr. Dillabough has been involved
the Shakespeare project since 2003 and since January 2007 managed the
preparation and execution of the bulk sample mining program for URSA Major.
This release was prepared by management of the Company who takes full
responsibility for its contents.
Some statements contained in this release are forward-looking and, therefore,
involve uncertainties or risks that could cause actual results to differ
materially. Such forward-looking statements include comments regarding mining
and milling operations, mineral resource statements and exploration program
performance. Factors that could cause actual results to differ materially
include metal price volatility, economic and political events affecting metal
supply and demand, fluctuations in mineralization grade, geological,
technical, mining or processing problems, exploration programs and future
results of exploration programs, future profitability and production.
FOR FURTHER INFORMATION PLEASE CONTACT:
URSA Major Minerals Incorporated Richard Sutcliffe, Ph.D., P.Geo President &
CEO (416) 864-0615 (416) 864-0620 (FAX)
URSA Major Minerals Incorporated Chris Chadder, C.A. CFO (416) 864-0615 (416)
864-0620 (FAX) Email: info@ursamajorminerals.com Website:
www.ursamajorminerals.com
URSA Major Minerals Incorporated Gus Garisto Investor Relations Cell: (416)
805-3106
The TSX has not reviewed and does not accept responsibility for the adequacy