RE: down we gofyi - after the close Denison Mines announced a production shortfall for next year (see below excerpt)
"The level of ore production is currently behind anticipated levels due largely to delays in permitting at Tony M and for completing ventilation shafts at the Colorado Plateau mines, as well as the impact of inexperienced mining crews. We now expect to have approximately 130,000 tons of material stockpiled before
conventional ore production commences. While these issues are being addressed,we anticipate having lower quantities of ore available for processing in 2008 which will impact 2008 production. We now anticipate 2008 production to be 1.7 to 2.1 million pounds U3O8 as compared to previous estimates of 2.9 million pounds U3O8"